Artboard 1Icon/UI/CalendarIcons/Ionic/Social/social-pinterestIcon/UI/Video-outline

Residential Focus - 9 May 2018

09 May 2018

9 min read

#Property, Planning & Development

Published by:

Eleanor Grounds, Christopher Yong

Residential Focus - 9 May 2018

Blessed Sydney Constructions Pty Ltd v Vasudevan [2018] NSWCATAP 98

In Blessed Sydney Constructions Pty Ltd v Vasudevan [2018] NSWCATAP 98 on 26 April 2018, the New South Wales Civil and Administrative Tribunal (the Tribunal) Appeal Panel looked at the extent of the Tribunal’s power to make a money order on a renewal application.

Facts

The Owner claimed for defects, the builder claimed amounts for works carried out.

On the day of the hearing, the Owner and the Builder executed a written agreement. The Builder withdrew its application and the Tribunal subsequently made a work order in relation to the Owner’s application that the Builder return to the Property and perform certain works under the contract and its agreed variations in a proper and workmanlike manner. The Owner was to be charged for five variations. The Owner was granted leave to renew its proceedings within 12 months if the work order was not complied with.

The Owner instituted renewal proceedings in the Tribunal, alleging the Builder had failed to complete the works subject of the work order. Further, three out of five variations appeared to have not been completed or invoiced.

The Tribunal varied its orders, requiring the Builder to pay the homeowner damages in the sum of $83,243.05, plus legal costs. 

Appeal

On appeal, the Builder argued the Tribunal did not have the power to award the Owner damages as an order for damages could not have been made under clause 8(4)(a) of Schedule 4 to the Civil and Administrative Tribunal Act 2013 (NSW) (NCAT Act), which limits the Tribunal’s powers on renewal to making any other appropriate order under the NCAT Act or enabling legislation as it could have made when the matter was originally determined. The relevant circumstance informing this argument was that the contract had not been terminated.

The Appeal Panel favoured an interpretation of clause 8(4)(a) that “as [the Tribunal] could have made when the matter was originally determined” should be construed as referring to orders that the Tribunal had authority to make when the matter was originally determined, whether those orders were appropriate or not in the circumstances at that time. In the case of an application under the HB Act, such orders include all those in s48O.

The Appeal Panel summarised its views on the proper construction of clause 8(4)(a) as follows:

  • on a renewal application, the Tribunal can make an order that is materially different from the order made when the proceedings were originally determined
  • such an order must be suitable or fitting in light of the general law principles, whether legal or equitable, and statutory provisions applicable to the type of relief claimed on the renewal application as well as all other relevant circumstances, whether occurring before or after the proceedings were originally determined, including the fact that the order originally made has not been complied with within the time specified in the order and that a renewal application has been made
  • such an order must be one that the Tribunal has authority to make under the NCAT Act or the relevant enabling legislation
  • such an order must be one that the Tribunal had authority to make when the proceedings were originally determined, having regard to the specific legislative provisions under which the original application was made, but the order does not have to be an order that would have been appropriate in the circumstances when the proceedings were originally determined.

The Appeal Panel found that the contract had been terminated between the work order and the renewal hearing. Accordingly it was not relevant that the contract had not been terminated when the work order was made.

In so finding, the Appeal Panel accepted that the Tribunal may not award substantial damages, representing the cost of completing incomplete work under a building contract, while the building contract remains on foot, and the builder remains in possession of the site and is carrying out work as required by the contract.

Given the contract was no longer on foot and its four criteria were met, the Appeal Panel held that the Tribunal below’s order for the Builder to pay the Owner damages was correctly made. As such, the appeal was dismissed. 

What does this mean? 

This decision is significant for parties who appear before the Tribunal on a renewal application. The Appeal Panel has interpreted the renewal powers widely and builders who may benefit from s.48MA in the Tribunal below by the making of a work order, should be mindful of the scope for its conversion to a money order on renewal.

Editorial: Christine Jones, Eleanor Grounds & Christopher Yong


In the media

HIA: Population helps maintain healthy building approvals
"New dwelling approvals have strengthened in Australia’s population and economic hotspots," explained Shane Garrett, HIA’s Senior Economist. Building approvals data for March released by the ABS today indicate that total new dwelling approvals grew by 2.6 per cent during the month and were 14.5 per cent higher than a year earlier (03 May 2018).  More...

New South Wales

South Sydney builder sentenced to home detention over fake insurance
A builder from south Sydney has been sentenced to eight months home detention after using fake home warranty insurance to win two building contracts, Minister for Innovation and Better Regulation Matt Kean said. The court was told he provided fraudulent home warranty insurance certificates to customers in Minto and Prestons in 2015 to retain his building contracts (03 May 2018).  More...

Unlicensed builders putting consumers in jeopardy
The rap sheet against Matthew Rixon was damning, for his 2015 offence, he was finally thrown behind bars. He was given an 18-month sentence with a 12-month non-parole period. Whilst the judgement intended to send a message to repeat offenders, the case underscored the problems which consumers – often elderly – face from unlicensed and unscrupulous builders and trade contractors (01 May 2018).  More...

NSW successfully calls for national report on liability for rectifying unsafe aluminium cladding
The NSW Government has successfully called for a national report to examine who is liable for having unsafe cladding rectified on buildings, Minister for Innovation and Better Regulation Matt Kean said. The report is the latest step in a series of ongoing reforms regarding the use of cladding across NSW (27 April 2018). More...

Published

Australian Bureau of Statistics

03/05/2018 Building Approvals, Australia, Mar 2018 (cat no. 8731.0)

Cases

New South Wales

Dimitropoulos v Capital Constructions Pty Ltd; Capital Constructions Pty Ltd v Dimitropoulos [2018] NSWCATAP 100
CONTRACT LAW – termination on notice – substantial breach – meaning of “substantial”.
REPUDIATION – election – manner by which repudiation can be accepted – reasonable time to make election – conduct in performance of contract while considering notice under contract.
COSTS – exercise of discretion.

Ingate v Andrews [2018] NSWCATAP 99
HOME BUILDING – Builder’s claim against owner for undocumented variations – Quantum Meruit – Relevant Principles – Application of Principles – Appeal Dismissed.

Carrigan v NSW Fair Trading [2018] NSWCATOD 60
ADMINISTRATIVE REVIEW – Home Building – Application for individual contractor licence – Where application rejected on basis that applicant did not meet requirements of an instrument made by the respondent – Whether the Tribunal is satisfied that the applicant has the requisite qualifications and experience to be a builder.

Blessed Sydney Constructions Pty Ltd v Vasudevan [2018] NSWCATAP 98
RENEWAL OF PROCEEDINGS – powers of Tribunal on renewal application – cl 8(4) of Sch 4 to the Civil and Administrative Tribunal Act 2013 (NSW) – construction of “any other appropriate order under this Act or enabling legislation as it could have made when the matter was originally determined” – whether Tribunal has power to make an order for the payment of money in place of a work order – Tribunal has power to make order for the payment of money by way of damages in this case even if such an order was not appropriate when the proceedings were originally determined.

Knox v Bollen; Bollen v Knox [2018] NSWCATAP 106
APPEAL – costs where proceedings settled – adequacy of reasons – Mr Knox (the homeowner) and Mr Bollen (the builder) applied for costs. Their applications arose from the settlement of their respective substantive applications (HB 16/32832 and HB 17/04418), which were brought under the Home Building Act 1989 (NSW). 

Grant v Gillham; Christopher J Grant Pty Ltd v Gillham [2018] NSWCATAP 104
APPEAL: Home building – Identity of contracting parties – Breach – Determination of compensation – Adequacy of reasons. 

SHMH Properties Australia Pty Ltd v City of Sydney Council [2018] NSWLEC 66
APPEAL – modification of development consent – development consent to change use of building to boarding house and associated alterations to building – deletion of deferred commencement conditions requiring submission of BASIX certificate – whether development is “BASIX affected development” – whether building is “BASIX affected building” – whether certain units in the boarding house are “dwellings” – modification refused. 

Central Projects Pty Ltd v Davidson [2018] NSWSC 523
BUILDING AND CONSTRUCTION – Progress payments – Effect of omission of information from a supporting statement under Building and Construction Industry Security of Payment Act 1999 (NSW) s.13(9) – Effect of failure to serve a supporting statement under Building and Construction Industry Security of Payment Act 1999 (NSW) s.13(7). 

Rekrut and Scott v Champion Homes Sales Pty Ltd; Champion Homes Sales Pty Ltd v Rekrut and Scott [2018] NSWCATAP 97
COSTS – NCAT Internal appeal – amount in issue in excess of $30,000 – r.38A of the Civil and Administrative Tribunal Rules 2014 (NSW) and cl.20(4) of the Consumer, Trader and Tenancy Tribunal Regulation 2009 (NSW) – no issue of principle COSTS – general rule that costs follow the event – application of the rule and discretion – no issue of principle.
Both appeals were from orders in proceedings in the Consumer and Commercial Division (file number HB 13/66604) arising out of home building work carried out by the builder for the owners.


Contacts:

Christine Jones, Partner - Construction & Infrastructure (Dispute Resolution) 
T: +61 2 8083 0477 
E: christine.jones@holdingredlich.com

Stefanie Dunnicliff, Senior Associate 
T: +61 2 8083 0464 
E: Stefanie.Dunnicliff@holdingredlich.com

Divya Chaddha, Associate 
T: +61 2 8083 0457
E: Divya.Chaddha@holdingredlich.com


Disclaimer

The information in this publication is of a general nature and is not intended to address the circumstances of any particular individual or entity. Although we endeavour to provide accurate and timely information, we do not guarantee that the information in this publication is accurate at the date it is received or that it will continue to be accurate in the future. We are not responsible for the information of any source to which a link is provided or reference is made and exclude all liability in connection with use of these sources.

Published by:

Eleanor Grounds, Christopher Yong

Share this