Developers and consent authorities will be intimately familiar with the mechanism for proponents to amend a development application (and more recently, modification application) before the application is determined.
The power to amend an undetermined application allows applicants to respond to matters raised, usually by Council, while the application is under assessment, or during class 1 appeal proceedings before the Land and Environment Court.
However, the power to amend an undetermined application has limits.
In two recent Registrar’s decisions, the Land and Environment Court found that proposed amendments to two development applications on appeal were outside the power to amend because the proposed amendments would push the development past the “tipping point” into being a new application.
These decisions were Goldcoral Pty Ltd v Richmond Valley Council [2023] NSWLEC 1540 (Goldcoral) and Reid v Woollahra Municipal Council [2023] NSWLEC 1611 (Reid). At the date of publication of this article, the Applicant in Goldcoral has filed a motion seeking review of the Registrar’s decision.
Goldcoral and Reid have confirmed:
These principles are looked at in more detail below.
For development applications lodged after 1 March 2022, sections 37 and 38 of the EPA Regulation 2021 allow an applicant to seek to amend a development application before it has been determined.
Under the previous EPA Regulation 2000 this power was contained in different terms in clause 55.
In Reid, the Registrar accepted that despite being in different terms, ss 37 and 38 of the EPA Regulation 2021 correspond to the former power in clause 55 of the EPA Regulation 2000.
The Registrar held that the reasoning in the extensive authorities relating to clause 55 of the EPA Regulation 2000 applied when considering the power and scope of subsection 37 and 38 of the EPA Regulation 2021.
In considering whether leave should be granted to amend a DA, the Court in Reid and Goldcoral adopted the questions posed by the Court on this issue in Radray Contructions Pty Ltd v Hornsby Shire Council (2006) 145 LGERA 292; [2006] NSWLEC 155:
The Applicants in both Reid and Goldcoral fell at the first hurdle, with the Court finding in both cases that the amendments proposed were outside the power available under the relevant regulation.
At its core, the power to amend is the power to change an application, not to propose a new or original application – the focus remains on whether the proposal can “answer the overall description and essence of the development as originally proposed”: Orico Properties Pty Ltd v Inner West Council [2017] NSWLEC 90 at [10] (Orico).
The ‘tipping point’ described by Robson J in Orico is where the extent of the amendments render the development so different as to constitute a new development application.
Unlike Reid, consideration of the amendments in Goldcoral did not focus on one element of the proposed amendment that pushed the development past the ‘tipping point’ as referred to by Robson J in Orico.
In Goldcoral, the development application was a concept DA for subdivision, clearing, earthworks, roadworks and other associated works.
The proposed amendments included a multi-dwelling housing lot and proposed community title subdivision (which were previously not proposed), a reduction in the total areas of residential subdivision and road reserve, a significant reduction in the proposed earthworks and abandoning previously proposed crown foreshore embellishment works.
To support this amendment, the applicant relied on several authorities where the Court had granted leave for amendments of a similar nature to certain elements of Goldcoral’s proposal.
The Registrar found that the Applicant’s proposed amendments had reached the “tipping point” without identifying any single amendment that pushed the development too far.
The Registrar found that the prior decisions referred to were not determinative as the Registrar was required to consider the cumulative effect of the amendment as a whole.
In Reid, the applicants sought amendments relating to the proposed built form, and substitution of the proposed use from a dual occupancy to a single dwelling.
The Council submitted that as a separate and distinct use, the change in use between the DA as lodged and the proposed amendment, would have changed the ‘essence’ of the development.
Further, and as a matter of practicality, the DA as lodged had been assessed as a dual occupancy. A change of the use of the proposed building to a single occupancy would warrant reassessment, further indicating that the amendment would constitute a new development application.
This was distinguished from the caselaw that an amendment that adds an additional type of development may fall within the power to amend a DA: see for example Australian Enterprise Holdings Pty Ltd (t-as AEH Group) v Camden Council (2010) 173 LGERA 226.
The distinguishing factor in Reid was the substitution of the proposed land use wholly for another.
The test undertaken by a consent authority is not concerned with why the amendments are being made or the impact of the changes.
While these factors may inform the exercise of discretion to accept a proposed amendment, the threshold question of whether there is power to amend the development application is confined to the scope of the amendments, and whether the changes to the proposed development are, as a matter of fact, so different as to constitute a new development application.
If you have any questions, please contact a member of our team below.
Disclaimer
The information in this publication is of a general nature and is not intended to address the circumstances of any particular individual or entity. Although we endeavour to provide accurate and timely information, we do not guarantee that the information in this newsletter is accurate at the date it is received or that it will continue to be accurate in the future.