Artboard 1Icon/UI/CalendarIcons/Ionic/Social/social-pinterestIcon/UI/Video-outline

Does 'termination' mean completion of works in Home Building Act warranty claims?

The recent decision in Howell v Talevski clarified that the issue of whether proceedings for breach of the warranties in section 18B of the Home Building Act 1989 (NSW) (HBA) have been commenced within time is ultimately a matter of contractual construction, and that termination of a contract does not render the works complete by relieving the builder of any further obligation to perform the works.

Facts

This case involves a claim by the plaintiff owner (Owner) against the defendant builder and structural engineer (Builder) regarding defective and incomplete work.

In 2007, the parties entered into two contracts. The first, in April 2007, was for the construction of foundations. The second, in May 2007, was for construction of a duplex on those foundations (Contract).

The Builder commenced work under the Contract in August 2007. The date for completion of the work was extended a number of times to a date after 17 July 2011. By August 2012, the works remained incomplete. The Contract was terminated in November 2012.

The Owner commenced proceedings on 17 July 2018 in NCAT alleging breach of the warranties in section 18B (Warranties) of the Home Building Act 1989 (NSW)(HBA). Those proceedings were subsequently transferred to the Supreme Court of NSW.

The Builder argued that the proceedings were commenced after the relevant limitation period had expired on the basis that on termination of the Contract, the works were ‘complete’, and so the limitation period commenced on the date of termination.

Legal issue(s)

The preliminary issues for the Court to determine included:

  • the length of the limitation period
  • when the limitation period commenced, which involved consideration of when the work was completed.

Decision

Stevenson J concluded the plaintiff had commenced proceedings within time on the following basis.

The limitation period for breach of the Warranties is seven years for all defects where the relevant contract was entered into before 1 February 2012. The subsequent amendments to the limitation period (reducing this to six years for structural defects and two years for non-structural defects) were not retroactive.

According to section 18E(1) of the HBA (in force in 2007), the limitation period for filing proceedings runs from:

  • "the completion of the work to which it relates, or
  • if the work is not completed:
    • the date for completion of the work specified or determined in accordance with the contract, or
    • if there is no such date, the date of the contract.”

In determining whether the provisions of section 18E(1)(a) or (b) applied, His Honour stated that “completion of residential building work” occurred on the date that the work was complete “within the meaning of the contract under which the work was done”, and not any definition within the HBA.

His Honour then concluded that the work under the Contract was not complete immediately prior to its termination, based on the definition of completion in the Contract. His Honour also concluded that the termination and discharge of the Builder’s contractual obligations did not render the works complete. 

Accordingly, His Honour concluded that the limitation provisions in section 18E(1)(b) applied to the claim, with the limitation period running from the date for completion of the work “specified or determined” under the Contract. 

The Court noted that the parties had agreed to extend the date for completion of the work to after 17 July 2011.

Accordingly, His Honour concluded that the proceedings were commenced within time as they were commenced within seven years of the date for completion.

Author: Christine Jones & Marie-Louise Scarf

In the media

Fears wharf strikes will bring construction to its knees
The construction industry has been dealt another blow as industrial action cripples ports across Australia, adding pressure to an already constrained construction materials supply chain (27 September 2021).  More...

$15 million to combat timber shortages
The Federal Government has invested an additional $15.1 million to combat the structural timber shortage faced by the housing and construction industry. The investment will be used to deliver bushfire-affected softwood to underutilised timber mills, targeting timber on Kangaroo Island that could provide enough timber for between 8,000 and 10,000 new houses (22 September 2021).  More...

NSW construction the exemplar industry
Australian Constructors Association CEO Jon Davies said the removal of the workforce cap reflects the positive response by construction workers to the call to get vaccinated but also the collaborative approach taken to reduce the risks of COVID transmission (21 September 2021).  More...

Industry welcomes decision to lift construction work force caps
Infrastructure Partnerships Australia welcomes the NSW Government’s announcement to lift construction workforce caps on sites from Monday next week (21 September 2021).  More...

Practice and courts

Culture in construction
The Cost of doing nothing report calculates that the estimated economic cost of lost wellbeing from work-related fatalities, injuries and illnesses in 2018 was $6.1 billion; the productivity cost of employees consistently working overtime was $708 million; the cost of mental ill-health was $643 million and the cost of higher incidence of male construction worker suicides compared to other industries was $533 million. This report and other information about the culture standard are available on the new culture in construction website.

HIA submissions
Proposed Wilton housing complying development code explanation of intended effect 24 September 2021.

Guide for design practitioners and engineers
Consult Australia, Engineers Australia and the Australian Institute of Architects have joined forces to develop the Guide for design practitioners and engineers to help their members tackle the recent NSW building confidence reforms. There are multiple new obligations on design practitioners, engineers and building practitioners throughout the life of a building under the NSW Design and Building Practitioners Act 2020 and the Design and Building Practitioners Regulation 2021.

Conflicts of interest – savings and transitional arrangements
Clause 71 of the regulation introduces savings provisions for certain conflict of interest situations where the certifier was appointed before 1 July 2020 and the work will be completed before 1 July 2022. The provisions relate to council-certified developments and to developments where the certifier gave advice on how to comply with the BCA deemed to satisfy provisions. For all the changes, access the amendment regulation.

Cases

Tanios v Baserite Constructions Pty Ltd [2021] NSWCATCD 85
BUILDING AND CONSTRUCTION – Home Building Act 1989 (NSW) – whether a building works agreement arose out of a compromise of prior proceedings – whether a consent work order in the prior proceedings was beyond the tribunal’s jurisdiction – renewal application by home owner on remitter from appeal panel – oral variation of building works agreement alleged by builder – whether oral variation is enforceable – cross application by builder for quantum meruit sum in respect of some building works performed following compromise of prior proceedings.

Jayasooriah v Wisdom Properties Group Pty Ltd [2021] NSWCATCD 84
BUILDING AND CONSTRUCTION – renewal of proceedings after work order – whether applicant can raise a fresh claim not the subject of the previous orders.

Addbuild Master Builders Pty Ltd v Stern [2021] NSWCATCD 83
BUILDING AND CONSTRUCTION – proper construction of payment provisions in clauses 12 and 14 of New South Wales Fair Trading residential building contract – damages – mitigation – work order – section 48MA of the Home Building Act 1989 (NSW).

Dodd v Balmain Projects Group Pty Ltd [2021] NSWCATCD 82
BUILDING AND CONSTRUCTION – Home Building Act 1989 (NSW) – major defect – whether any defects are a major defect – whether a work or a money order should be made in respect of major defects as agreed or found.

Bourke v Wincrest Group Pty Ltd [2021] NSWCATCD 81
COSTS – no issue of principle.

Betts v Harman [2021] VCC 1349
SALE OF LAND – sale by owner builder – failure to annex required insurance as provided by section 137B of the Building Act 1993 – whether parties contracted out of the purchaser’s entitlement to rescind – whether purchaser elected to affirm contract – whether precluded from rescission by waiver estoppel – whether time for provision of insurance material extended by terms of contract – whether purchaser’s failure to settle on time precludes purchaser from rescinding.

Bajimaya v Reward Homes Pty Ltd [2021] NSWCATAP 297
HOME BUILDING – jurisdiction – agreement to enter into a building contract.
Civil and Administrative Tribunal Act 2013 (NSW), sections 60, 80, 81, Scheme 4 clause 12; Civil and Administrative Tribunal Rules 2014 (NSW), rr 38, 38A.

Day v Quince’s Quality Building Services Pty Ltd [2021] NSWCATAP 296
BUILDING AND CONSTRUCTION – construction and interpretation of home building contract – clause 14 of the BC4 residential building contract – whether tribunal erred in interpretation and application of the clause.

Hume Plasterboard Pty Ltd v Best Interiors Aust Pty Ltd & Ors (No.2) [2021] NSWDC 514
COSTS – whether part of successful defendant’s costs should not be paid because of non-compliance with procedural directions – whether costs payable by unsuccessful defendant should be paid on indemnity basis – whether Bullock order should be made.

De Marco v Macey [2021] NSWCATAP 291
HOME BUILDING – alleged procedural unfairness – alleged inadequate consideration of evidence – no issue of principle.

Mick Fabar Constructions Pty Ltd v Nicholls; Nicholls v Mick Fabar Constructions Pty Ltd [2021] NSWCATAP 290
HOME BUILDING – jurisdiction of Tribunal – appeal on a question of law – breach of contract – breach of statutory warranty – method of rectification – assessment of cost of rectification – indemnity costs.

Dyna Constructions Pty Ltd v Bocco Developments Pty Ltd [2021] NSWDC 507
BUILDING AND CONSTRUCTION – Australian consumer law.
BUILDING AND CONSTRUCTION – Home Building Act 1989 (NSW) – insurance – false or misleading applications.

Nova Home Developments Pty Ltd v Manzala [2021] NSWCATAP 287
PROCEDURAL FAIRNESS – failure to allow cross-examination.
APPEALS – leave to appeal – whether decision against the weight of evidence.
Civil and Administrative Tribunal Act 2013 (NSW); Home Building Act 1989 (NSW).

Leahy v Watermin Drillers Pty Ltd [2021] NSWCATAP 281
APPEAL – written contract for water drilling – oral variation – whether tribunal erred in preferring oral evidence of contractor – appellant claiming denial of natural justice due to lack of waterflow evidence – no expert evidence provided before tribunal of waterflow to support appellant’s claims – appeal dismissed.

Allianz Australia Insurance Limited v Rawson Homes Pty Ltd [2021] NSWCA 224
CONTRACTS – construction – construction of insurance contract – where policy insured against damage to construction projects – where houses under construction damaged in hailstorm – where policy provided for application of “deductible” – whether “deductible” to be applied in respect of each house under construction, or whether to be applied only once to the total sum to be paid for damage caused by the hailstorm.

Disclaimer
The information in this publication is of a general nature and is not intended to address the circumstances of any particular individual or entity. Although we endeavour to provide accurate and timely information, we do not guarantee that the information in this article is accurate at the date it is received or that it will continue to be accurate in the future.

Share this